A random generator of resource-constrained multi-project network problems

被引:46
作者
Browning, Tyson R. [1 ]
Yassine, Ali A. [2 ]
机构
[1] Texas Christian Univ, Neeley Sch Business, Ft Worth, TX 76129 USA
[2] Univ Illinois, Dept Ind & Enterprise Syst Engn, Urbana, IL 61801 USA
关键词
Project scheduling; Multi-project scheduling; Resource constraints; Random network generator; Network complexity; COMPLEXITY;
D O I
10.1007/s10951-009-0131-y
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Many scheduling problems in project management, manufacturing, and elsewhere require the generation of activity networks to test proposed solution methods. Single-network generators have been used for the resource-constrained project scheduling problem (RCPSP). Since the first single-network generator was proposed in 1993, several advances have been reported in the literature. However, these generators create only one network or project at a time; they cannot generate multi-project problems to desired specifications. This paper presents the first multi-network problem generator. It is especially useful for investigating the resource-constrained multi-project scheduling problem (RCMPSP), where a controlled set of multi-project test problems is crucial for analyzing the performance of solution methods. In addition to the single-project characteristics handled by existing network generators-such as activity duration, resource types and usage, and network size, shape, and complexity-the proposed generator produces multi-project portfolios with controlled resource distributions and amounts of resource contention. To enable the generation of projects with desired levels of network complexity, we also develop several theoretical insights on the effects of network topology on the probability of successful network generation. Finally, we generate 12,320 test problems for a full-factorial experiment and use analysis of means to conclude that the generator produces "near-strongly random" problems. Fully "strongly random" problems require much greater computational expense.
引用
收藏
页码:143 / 161
页数:19
相关论文
共 40 条
[1]   DAGEN: A generator of testsets for project activity nets [J].
Agrawal, MK ;
Elmaghraby, SE ;
Herroelen, WS .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 90 (02) :376-382
[2]  
Alvarez-Valdez R., 1989, Advances in Project Scheduling, P113
[3]  
[Anonymous], REV FRANCAISE RECHER
[4]  
[Anonymous], 1967, THESIS MIT
[5]   OPTIMAL REDUCTION OF 2-TERMINAL DIRECTED ACYCLIC GRAPHS [J].
BEIN, WW ;
KAMBUROWSKI, J ;
STALLMANN, MFM .
SIAM JOURNAL ON COMPUTING, 1992, 21 (06) :1112-1129
[6]  
BROWNING TR, 2009, RESOURCE CONSTRAINED
[7]  
Dar-EL E. M., 1973, AIIE Transactions, V5, P343, DOI 10.1080/05695557308974922
[8]  
Davis E. W., 1975, AIIE Transactions, V7, P132, DOI 10.1080/05695557508974995
[9]   COMPARISON OF HEURISTIC AND OPTIMUM SOLUTIONS IN RESOURCE-CONSTRAINED PROJECT SCHEDULING [J].
DAVIS, EW ;
PATTERSON, JH .
MANAGEMENT SCIENCE SERIES B-APPLICATION, 1975, 21 (08) :944-955
[10]   A RANDOM ACTIVITY NETWORK GENERATOR [J].
DEMEULEMEESTER, E ;
DODIN, B ;
HERROELEN, W .
OPERATIONS RESEARCH, 1993, 41 (05) :972-980