The impact of disruption and delay when compressing large projects: going for incentives?

被引:41
作者
Howick, S [1 ]
Eden, C [1 ]
机构
[1] Univ Strathclyde, Dept Management Sci, Glasgow G1 1QE, Lanark, Scotland
关键词
project management; risk; disruption and delay; simulation;
D O I
10.1057/palgrave.jors.2601045
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Demands by clients for earlier delivery after a project has started are increasing. This paper investigates the consequential disruption and delay that follows from the contractor accepting these demands. Explorations an carried out using a System Dynamics model based upon a large model constructed to represent the complexity of a claim for disruption and delay in relation to a specific mega-project. The model used for the explorations has been validated further using information gathered during work on other claim projects. The model enables the impact of disruption and delay resulting from the holistic and dynamic impact of a compressed delivery date to be assessed in relation to two specific and typical options. Use of the model suggests that the probability seems slight of finding the highly specific circumstances where there is any certainty in an outcome of early delivery at little extra cost.
引用
收藏
页码:26 / 34
页数:9
相关论文
共 45 条
[1]  
Abdel-Hamid T., 1991, Software Project Dynamics: An Integrated Approach
[2]   Modeling for litigation: Mixing qualitative and quantitative approaches [J].
Ackermann, F ;
Eden, C ;
Williams, T .
INTERFACES, 1997, 27 (02) :48-65
[3]  
[Anonymous], PROJ MANAGE J
[4]   LEARNING-CURVES IN MANUFACTURING [J].
ARGOTE, L ;
EPPLE, D .
SCIENCE, 1990, 247 (4945) :920-924
[5]  
BENNETT P, 1997, MULTIMETHODOLOGY THE, P59
[6]  
Chapman C.B., 1997, PROJECT RISK MANAGEM
[7]  
Cooper K.G., 1993, PROJECT MANAGEMENT J, V24, P17
[8]   NAVAL SHIP PRODUCTION - A CLAIM SETTLED AND A FRAMEWORK BUILT [J].
COOPER, KG .
INTERFACES, 1980, 10 (06) :20-36
[9]  
COOPER KG, 1999, PMNETWORK JUL, P43
[10]  
COOPER KG, 1997, NATO ASI SER, P89